The MBTA plans 100 days of scheduled service outages in 2027, and the longest ones for riders north of Boston are a nine-day Orange Line closure between North Station and Ruggles from May 15 to 23, a 10-day Blue Line closure between Bowdoin and Airport from June 18 to 27, and nine days without Green Line service between Government Center and the East Somerville and Union Square stations from November 13 to 21.
The agency published the 2027 construction schedule on Thursday, November 19. It put the 100 days against 132 this year, 190 in 2025 and 274 in 2024, and said most subway interruptions will fall on weekends. Dates can change because of weather or construction needs, the MBTA said, and each interruption will be announced in advance with shuttle bus and alternate route information.
Before any of that, the Blue Line shuts down for nine days next month. That closure and the full 2027 list for the lines that serve Malden, Medford, Somerville, Charlestown, Revere, Cambridge and the North Shore are below.
First: Blue Line, December 12 to 20
Blue Line service will be suspended between Bowdoin and Orient Heights for nine straight days, December 12 through 20, for full-depth track reconstruction, new ties and rail, and resurfacing, according to the MBTA’s December construction notice. Trains are not listed as suspended between Orient Heights and Wonderland.
Free, accessible shuttle buses will run from Orient Heights to Haymarket, where riders can connect to the Orange and Green lines. The MBTA tells riders to budget an extra 40 minutes. Accessible van service will be offered in downtown Boston only.
The agency will hold a virtual public meeting on the Blue Line work and the alternatives on November 30. It said details would be posted at MBTA.com/Events.
Also in December, the Green Line will be suspended from North Station west through the central tunnel for four days, December 4 through 7, for signal work. The notice lists the closed stretch as North Station to Babcock Street on the B branch, St. Mary’s on the C, Brookline Hills on the D and Heath Street on the E, with shuttle buses and an extra 35 minutes of travel.
Orange Line in 2027
Every Orange Line suspension on the 2027 list begins at North Station or south of it. None covers the stations from Oak Grove through Malden Center, Wellington, Assembly, Sullivan Square and Community College, but riders from those stations who travel through downtown will meet each one.
- March 6 and 7 (weekend): Back Bay to Forest Hills, for tunnel inspections and work at Ruggles Station.
- May 15 to 23 (nine days): North Station to Ruggles, for rail replacement through the whole closed area, full-depth track replacement, new ties and surfacing.
- July 10 and 11 (weekend): North Station to Back Bay, for radio upgrades.
- October 8 to 11 (four days): North Station to Back Bay, for two new accessible transfer elevators at Downtown Crossing.
Green Line Extension and the Lowell Line
The closure that reaches Somerville and Medford directly comes in the fall. Green Line service is to be suspended between Government Center and both East Somerville and Union Square for nine days, November 13 to 21, for rail replacement, full-depth track replacement, tie replacement and work on complicated track sections.
On the first weekend, November 13 and 14, the suspension stretches all the way to Medford/Tufts so crews can remove the Broadway Utility Bridge. The Commuter Rail’s Lowell Line, which runs beside the extension, is listed for “some impacts to regular schedules” that same weekend for the same bridge removal.
Earlier in the year, the central tunnel signal work continues with Green Line service suspended between North Station and Babcock Street, Kenmore and Heath Street on the weekends of January 9 and 10, February 6 and 7, February 20 and 21, and February 27 and 28, and for nine days from January 16 to 24. The MBTA said that work finishes the new signal system the tunnel needs before the new Type 10 cars arrive. Tunnel inspections close the same stretch on the weekends of September 18 and 19 and September 25 and 26.
Blue Line in 2027
- June 18 to 27 (10 days): Bowdoin to Airport, for rail replacement, full-depth track replacement, ties and surfacing.
- October 23 and 24 (weekend): radio upgrades, with fiber-optic and radiating cable installed in the tunnels.
Red Line north of the river
- January 30 and 31 (weekend): suspended between Alewife and Kendall/MIT for tunnel inspections.
- July 17 and 18, July 24 and 25 (weekends): suspended between Kendall/MIT and JFK/UMass for radio upgrades and tunnel inspections.
- November 6 and 7, November 13 and 14 (weekends): trains share a single track between Alewife and Harvard for radio upgrades.
The rest of the Red Line work is on the south side: JFK/UMass to Quincy Center April 8 to 12, Broadway to North Quincy and JFK/UMass April 24 and 25, and JFK/UMass to Braintree for nine days, August 7 to 15.
Commuter Rail: Newburyport/Rockport Line
The only work listed for the Newburyport/Rockport Line is at its northern end. Track tie replacement will disrupt off-peak weekday service, 9 a.m. to 3:30 p.m., between Newburyport and Ipswich in weekly blocks from March 8 through June 30. The stations at Lynn, Swampscott, Salem and Beverly are outside the listed segment. The schedule lists nothing for the Haverhill Line.
The MBTA said every date is subject to change. Riders planning around any of them should check MBTA.com/PlannedWork closer to the day.
Why the T says fewer closures are needed
“In 2023, 65 percent of the system was found to be out of State of Good Repair,” Interim Transportation Secretary and MBTA General Manager Phillip Eng said in the release. He said the weekend and multi-day closures since 2024 have replaced hundreds of thousands of feet of rail and upgraded much of the signal system.
The agency’s count: spot rail replacement on more than 134,500 feet of the Red Line, 69,250 feet of the Orange Line, 40,360 feet of the Green Line and 18,800 feet of the Blue Line, almost 20,000 feet of continuous welded rail on the Orange Line, and 72 miles of new signal cable in the Green Line’s central tunnel in the past year. Nearly half the signal control points and 65 percent of track circuits systemwide have been renewed, it said.
For 2027 the priorities are finishing signal upgrades on the Red and Orange lines and in the Green Line tunnel, track maintenance on every subway line, and new radio communications across the system.
The schedule came out the same day Eng told the MBTA board that average weekday ridership topped one million trips in October for the first time since February 2020. The agency said October was 4 percent above September and 9 percent above October 2025.