The playground that neighbors spent two years raising money for on the site of the former Gerry School opened to the public on Sunday morning, November 15, with a ribbon cutting that the Marblehead Current reported drew about 200 people. The Park on Elm, as the Friends group that drove the project calls it, has swings, a wooden play boat, a circular lawn ringed with young trees and a basketball court, all on the paved lot at the corner of Elm Street that once served the school.
The town’s own records tell the story of how it was built and what the public paid for. Select Board minutes, bid results, a Recreation and Parks Commission briefing and the town’s American Rescue Plan Act ledger show two separate construction contracts totaling $631,105, a federal recovery allocation that started at $100,000 and was raised twice, and a 19th-century stone cistern that nobody knew was under the lot until the excavators hit it.
A school lot split in two
The Gerry School, a brick elementary school on Elm Street, closed years ago. According to a presentation that Brendan Callahan gave the Recreation and Parks Commission on September 10, 2025, the property was divided: the school building went to a condominium conversion, and the parking area behind it was kept for a public park. A neighborhood group, which the commission’s minutes call the Friends of Elm Street Park, formed to raise money for it.
The project was always planned in phases. Phase one was the site itself: tearing out the old pavement, playground and fencing, regrading, and putting in new asphalt walks and parking, granite curbing, a fence, loam and seed. Phase two was the playground.
Federal money first
The town’s first contribution came from its share of the American Rescue Plan Act, the pandemic recovery law that sent Marblehead $6,144,029.93 in two tranches between July 2021 and September 2022. A report the town published on the status of that money as of February 28, 2024, lists “Gerry School Playground and Park Improvement” among the projects funded in fiscal 2024, at $100,000. It sat on that list alongside $1,426,200 for the Rail Trail bridges at Lead Mills, $500,000 to replace the town’s fiber connection and $100,000 for design work at Redd’s Pond. At that point the town had $576,903 of recovery money left unspent and $13.5 million in requests it could not fund.
Four bids, and the low one from Swampscott
The town put phase one out to bid in the fall of 2024 under Chapter 30, Section 39M, the state law for public works contracts. The invitation to bid, issued through the Select Board as the awarding authority, said documents would be available November 7, 2024, set a site briefing for November 14 and called for electronic bids by 10 a.m. on December 3. Bidders had to post a 5 percent bid bond and pay state prevailing wages.
Four companies answered, and the town posted the results of the December 3 opening:
- Raffaele Construction Inc. of Swampscott, $184,105 base bid, plus $14,000 for Alternate 1, a new wooden fence;
- Belko Landscaping of Salem, New Hampshire, $192,000 plus $34,000 for the fence;
- J.J. Phelan and Son Co. Inc. of Tewksbury, $210,000 plus $20,000;
- Landscaping By J Michael of Marshfield, $256,902 plus $25,997.
On December 11, 2024, the Select Board, with Erin M. Noonan, Dan Fox, M. C. Moses Grader, Bret T. Murray and Alexa J. Singer present, voted to award Raffaele Construction the base bid of $184,105 for what the minutes call the Elm Street Park Improvement project, “aka Gerry school.” Twelve days later, at a remote meeting on December 23 attended by Noonan, Fox and Singer, the board added the $14,000 fence alternate to the Raffaele contract on its consent agenda.
The same consent agenda carried an increase in the project’s ARPA allocation. The minutes record it as “one hundred nine thousand four hundred and ninety dollars ($123,490.00),” so the words and the figures do not agree, and the town’s final ARPA expenditure report, which the board accepted at the same meeting, was attached to the minutes but is not posted with them. Either way, the federal share grew past the original $100,000 to cover the phase one contract. That December 23 meeting was the board’s last of the year, and the final ARPA report was adopted on a roll call of Fox, Singer and Noonan, all in favor.
What the digging turned up
By the time Callahan briefed the Recreation and Parks Commission in September 2025, Raffaele’s crews were on the site doing the parking lot, fence and walking paths. The Friends group had paid for work outside the town’s contract, including water service to the park and a conduit for a future electric vehicle charging station. Recovery money and Friends money together had hired a landscape architecture firm, Crowley Cottrell, to design both phases.
Then the excavators found the cistern. The minutes describe it as a previously unknown cistern from the 1800s. The Friends paid for the investigation, and the town paid $66,000 from its own funds to fill and cap it. The find had a second effect: it produced a large amount of granite. The original design had a path on the left side of the park running to a set of stairs, but the slope proved too steep, and the stairs were priced at $30,000 the town did not have, so the plan had been to dead-end the path and come back later. The salvaged granite was used instead for the stairs and for stepping stones, and the commission asked whether some could be spared for the stairs at Fountain Park. The Current reported Sunday that granite from the cistern was also turned into the benches on the playground.
Callahan told the commission that 10 percent of the playground cost would be held back for maintenance and that accessibility under the Americans with Disabilities Act would go beyond the minimum. The minutes also record a funding shortfall for phase two of between $20,000 and $29,000, and open questions about whether the public would have access to the stairs, which lead toward the condominiums.
The $433,000 playground
The shortfall was closed over the following months. On January 7, 2026, at an 11 a.m. hybrid meeting at Abbot Hall with Fox in the chair and Grader, Noonan, Singer and James R. Zisson present, the Select Board voted unanimously to award Contract 26-09, Phase II of the Gerry School Playground Improvements, to Belko Landscaping LLC for $433,000. Belko had been the second-lowest bidder on phase one a year earlier. The same morning the board awarded a $99,130 contract to Raffaele Construction to expand Waterside Cemetery and approved contracts for an overhead door at the public works yard and 50 replacement windows at the Hobbs House.
Added together, the two Elm Street awards, $198,105 to Raffaele and $433,000 to Belko, come to $631,105 in town contracts, before the $66,000 the town spent on the cistern and the design and extra work that the Friends paid for directly.
What the neighbors raised
How much of that was private money is not spelled out in the town’s posted records. Phase one was funded through ARPA, according to the commission minutes, and phase two was paid for mainly from donations. The Current reported that the Friends of the Park on Elm, which grew to a 20-member board, raised more than $500,000 from hundreds of donors, that the town’s federal contribution was about $200,000, and that the all-in cost including landscaping, trees, irrigation, parking and the basketball court landed between $600,000 and $700,000. One of the organizers, Jessica Murphy, told the paper that almost every household in that part of town had a hand in it.
The campaign began, by the organizers’ account to the Current, after parents grew worried about the condition of the old school playground, where a child had been cut on a piece of metal equipment.
What is next
The town has not posted anything about the opening. As of Sunday afternoon the Recreation and Parks Department’s Playgrounds page still listed five town playgrounds, Gatchell, Gerry, Hobbs, Orne and Reynolds, and the Gerry it describes is the older Gerry Playground on Stramski Way, home of Header’s Haven, not the new park on Elm Street. The commission minutes left open whether the stairs on the left side of the park are public, and the Fountain Park stairs that the commission hoped to build with leftover granite were still in design at the time.
The Select Board’s minutes for 2024 and 2026 and the Recreation and Parks Commission’s September 2025 minutes are posted on the town website, along with the invitation to bid and the bid results.
Sources: Marblehead Select Board minutes of December 11, 2024, December 23, 2024 and January 7, 2026; Recreation and Parks Commission minutes, September 10, 2025; the town’s ARPA Projects Report Update of February 29, 2024; the invitation to bid and bid results for the Elm Street Park Improvement Project; the town’s Playgrounds page; and the Marblehead Current’s report on Sunday’s opening.